Cochin Port unions seek ICTT extension disclosure
The Hindu BusinessLine··31 Aug
Cochin Port Joint Trade Unions Forum demanded disclosure of the rationale for a reported two-year extension to the Vallarpadam ICTT operator. India Gateway Terminal Pvt Ltd, a DP World company, has run the terminal since February 2011. Unions said it handled 0.77 million TEUs in 2025-26. Phase I capacity is 1.2 million TEUs a year.
Prism
What It Means For You
- Port users and workers are seeking year-wise throughput and revenue-share figures before any further concession.
- Pending claims, counterclaims and litigation status were listed among disclosure demands.
- Dredging cost burdens on the Port Authority remain part of the unions' public questions.
What's Happening
- The forum questioned an extension reportedly based on a conciliation committee headed by former Ports Secretary Gopalkrishna.
- It argued settling a dispute should not create perpetual concessions for the operator.
- Before Vallarpadam, the operator handled 0.32 million TEUs at the Rajiv Gandhi Container Terminal.
What The Terminal Was Built For
- ICTT was commissioned to develop Kochi as an international transshipment hub.
- Ultimate projected capacity is 2.5 million TEUs a year.
- After 15 years at Vallarpadam, 2025-26 throughput stood at 0.77 million TEUs.