Assam completes Rs 7 crore Saraighat Bridge rehabilitation
India
Archived — This article has been archived. The information may be outdated.

Assam completes Rs 7 crore Saraighat Bridge rehabilitation

The Indian Express··18 Sept

Northeast Frontier Railway completed a Rs 7 crore rehabilitation of Assam's Saraighat Bridge, commissioned in 1962. Work ran from July 13, 2026 to September 15, 2026. NFR CPRO Kapinjal Kishore Sharma said inspections found damage to the road deck, expansion joints and steel members. Eight of 11 expansion joints were repaired to support Delhi-Guwahati rail movement.

Prism

What It Means For You

  • Officials said the repairs aim to keep the Delhi-Guwahati rail link safer after decades of wear.
  • Road-deck sections were recast and given longer curing time than earlier quick pothole fixes.
  • Traffic still uses the Brahmaputra crossing while the strengthened span returns to regular service.

What's Happening

  • The Rs 7 crore project began on July 13 and finished on September 15, 2026.
  • Eight damaged expansion joints out of 11 on the bridge were dismantled and repaired.
  • Supporting steel members were strengthened where distress had been found.

Why the Span Needed Work

  • After more than 60 years, water had seeped through cracked concrete and damaged deck sections.
  • Earlier pothole repairs between January and May 2026 failed again under heavy vehicles.
  • Saraighat remains a key rail and road link between Assam, the Northeast and the rest of India.