Mumbai-Goa highway has 8 km left with Rs 2,000 crore
India
Archived — This article has been archived. The information may be outdated.

Mumbai-Goa highway has 8 km left with Rs 2,000 crore

The Indian Express·

About 8 km of work remains on five packages in the Maharashtra stretch of the 592-km Mumbai-Goa highway, with cost overrun estimates above Rs 2,000 crore on the pending section, The Indian Express reported. Union Minister Nitin Gadkari said on September 9 he was ashamed of delays and would skip the inauguration expected next year. MoRTH Secretary V Umashankar said.

Prism

What It Means For You

  • Completion of the last 8 km would link Mumbai and Panaji once Goa's border-to-capital stretch is done.
  • Umashankar said officials target finishing all pending work by April next year on the Maharashtra side.
  • Delay costs on the section have fed into a wider 44 percent rise in Maharashtra's project estimate.

What's Happening

  • Five of 13 packages in the 472-km Maharashtra section still need bypasses, a bridge, flyover and hill cutting.
  • Gadkari spoke at a 5.15-km Porvorim corridor opening in Goa on September 9 about embarrassment over delays.
  • Contractors cited cash flow, loan defaults, land acquisition and local protests as reasons for slow progress.

Why NH-66 slipped timelines

  • Parliament was told in 2016 the highway would finish by December 2018, later revised to 2021.
  • Maharashtra's cost estimate rose from Rs 12,532 crore to over Rs 18,100 crore, officials said.
  • MoRTH now wants clearances and about 90 percent land acquisition done before contractors are awarded work.