Cabinet clears Rs 1,86,405 crore green corridor
Business

Cabinet clears Rs 1,86,405 crore green corridor

The Indian Express··30 Sept

The Union Cabinet on Wednesday approved Green Energy Corridor Phase-III with a total outlay of Rs 1,86,405 crore. The scheme targets evacuation of up to 135 GW of renewable energy across states by 2032-33. It allocates Rs 1,36,378 crore for intra-state transmission and Rs 50,000 crore for 50 GWh of battery storage. Central financial support is Rs 54,082 crore.

Prism

What It Means For You

  • Central aid is meant to offset intra-state transmission charges that feed into power tariffs.
  • Battery storage in the plan is intended to cut peak-hour curtailment of solar power.
  • State transmission utilities will run the scheme, with greenfield lines bid competitively.

What's Happening

  • GEC-III is the first Green Energy Corridor phase with a dedicated battery storage component.
  • About 21 GW of renewables still move on temporary grid links while dedicated lines catch up.
  • During April-June, grid operators curtailed 8,133 GWh of solar output, MNRE told Parliament.

Why the corridor matters

  • India's renewable peak curtailment has grown as capacity outpaced transmission build-out.
  • GEC Phase-I covered eight states; Phase-II targets seven states with thousands of circuit km.
  • The Cabinet statement links the scheme to a 900 GW non-fossil capacity goal by 2035.