South Central Railway adds 6.9 MW rooftop solar capacity
The Hindu BusinessLine·
South Central Railway commissioned 6.9 megawatts of rooftop solar power over 31 months under the Prime Minister’s Surya Ghar Yojana. As of October 31, Secunderabad Division had 2.93 MWp, Hyderabad 2.60 MWp, Nanded 0.50 MWp and Lalaguda Workshop 0.87 MWp. Panels sit on rooftops across those railway units. The scheme launched on February 13, 2024.
Prism
What It Means For You
- The projects generate power at railway establishments, cutting reliance on conventional electricity at those sites.
- Installations cover Secunderabad, Hyderabad and Nanded divisions plus the Lalaguda workshop.
- General Manager Sanjay Kumar Srivastava said Railways carries a duty to build cleaner transport networks.
What's Happening
- SCR said the 6.9 MW came online across its jurisdiction during the last 31 months.
- Secunderabad leads the commissioned capacity at 2.93 MWp as of October 31, 2026.
- The Surya Ghar Yojana aims to expand rooftop solar and reduce dependence on conventional energy.
How The Capacity Splits
- Hyderabad Division accounts for 2.60 MWp of the commissioned rooftop total.
- Nanded Division has 0.50 MWp and Lalaguda Workshop 0.87 MWp.
- The national rooftop scheme began on February 13, 2024.