IAF expects 16 to 18 Tejas jets delivered by March
Hindustan Times·
The Indian Air Force told HAL it will accept delayed Tejas LCA Mk-1A fighters by March 31, 2027, officials said Monday. HAL committed to deliver 16 to 18 jets after a November 16 review. The IAF will take aircraft without relaxing capability requirements. Hardware issues including weapons trials are resolved, and radar software fixes are in final stages.
Prism
What It Means For You
- Squadron crews awaiting Mk-1A jets can plan conversion training around the March 2027 acceptance date.
- HAL must secure CEMILAC release-to-service documents before handing fighters to the IAF.
- First Mk-1A deliveries slipped about two years from the original March 2024 target.
What's Happening
- Air Chief Marshal Ashutosh Dixit and HAL chairman Ravi K attended the November 16 meeting.
- HAL placed two orders totalling 180 Mk-1A fighters worth a combined Rs 1.1 lakh crore.
- The IAF operates 29 fighter squadrons against an authorised strength of 42.5 squadrons.
Mk-1A programme delays
- GE Aerospace's late F404-IN20 engine shipments contributed to missed 2024 delivery deadlines.
- HAL now aims to complete the 2021 order of 83 jets in three to four years.
- The air force currently flies 38 Tejas Mk-1 aircraft as Mk-1A induction nears.