A 30-month flyover is in its tenth year. Bengaluru plans 11 more.
That flyover is in Ejipura, and it is still not open. The city's new plan adds 11 elevated corridors and two tunnels. Here is the whole story in 13 short stops, built from the government's own documents.
Start the rideRead this before? Skip to what's new, stop 13
₹31,516 crore at current government estimates. Costs change as projects are tendered and built.
Everyone agrees on the problem.
Bengaluru's traffic is broken. Citizens say it. Experts say it. The government says it too.
So this is not a fight about whether to act. It is a fight about what to pour the money into. Concrete for cars, or capacity for people.
Three projects. One big bill.
Here is what is on the table right now, at the government's own estimated cost.
Sources: OpenCity corridor DPR tracker, Outlook, The News Minute. Flyover figure is the sum of DPR costs.
A new road is an invitation.
Build a faster road and driving gets easier. So more people drive. Within a few years the new road is as full as the old one. Traffic engineers call this induced demand. Tap through it.
This is not a theory about some other city. It is written into the paperwork.
An IISc Sustainable Transportation Lab analysis of the Hebbal short tunnel says it just moves the jam to where the tunnel starts and ends. The project's own detailed report shows that by 2047 the tunnel runs at or beyond full capacity in every scenario it modelled.
Sources: IISc Sustainable Transportation Lab analysis and Hebbal tunnel DPR, as reported by The News Minute, Sept 16, 2026.
Same width. 40 times the people.
Road space in Bengaluru is fixed. You cannot widen your way out. So the real question is how many people a strip of land can move.
Figure from Prof. Ashish Verma, IISc Sustainable Transportation Lab, via Down To Earth. Each square is one lane's worth of people.
What this compares: how many people each mode can carry in the same width of road space. It is not a forecast for these specific Bengaluru projects.
Flyovers also carry the fewest people per rupee. About seven in ten vehicles in Bengaluru are two-wheelers, and campaigners say they will be kept off the new flyovers. The longest one, 28 km, will charge a toll for 30 years.
Sources: transport department data via Deccan Herald (87 lakh two-wheelers of 1.28 crore vehicles, July 2026); Deccan Herald on the tolled 28 km corridor; Dear DK campaign on two-wheeler access.
Road capacity fills up. Track capacity does not.
A road takes whatever traffic arrives. A train runs on a track nobody else can enter, on a timetable. That is why a 30 minute metro ride today is still close to a 30 minute ride in 2056, however many vehicles the city adds.
A flyover shares the same fate as every road. When IISc tested an earlier, similar flyover plan for Bengaluru against a metro on the same route, this is what it found.
IISc study (Verma, Vajjarapu, Allirani) of the 2019 elevated corridor proposal, using the government's own traffic data, as reported by Deccan Herald. The current corridors are a different set, but the physics is the same.
Some of it never comes back.
Traffic can be fixed later. Trees, lakes and years of your life cannot.
The trees
The project report for the Indiranagar flyover counts 89 trees in the way. Residents walked the route and counted over 749.
Source: Deccan Herald, June 22, 2026; The Federal.
● in the report ○ found on the ground, not in the report
Hebbal Lake
The lake takes the stormwater that runs off north Bengaluru. The short tunnel is dug 18.5 m deep, open trench style, a few metres from its edge.
Days before a High Court hearing, the lake authority handed over about 3 acres of lake land for the project. No environmental study has been made public, even though ₹75 lakh was budgeted for one. IISc says the tunnel entrance sits at the lowest point and is very likely to flood.
Source: The News Minute / Mongabay-India, Sept 16, 2026.
Distance as per DPR drawings cited in the High Court petition. Simplified, not to scale.
Your street, for years
The Ejipura flyover is 2.4 km long. It was supposed to take 30 months. Work began in 2017. It is now in its tenth year, and still not open.
The Indiranagar corridor that plugs into it is 5.2 km, more than twice as long. Its deadline is 24 months. On a road that was just re-concreted.
Sources: The News Minute on the Ejipura flyover; Deccan Herald, Oct 12, 2026; The Federal, June 13, 2026.
Lalbagh
The big tunnel passes under Lalbagh and reportedly needs around 5 acres of it. On August 24 a new law allowed up to 5% of any government park to be given away for public projects. For Lalbagh, that is about 12 acres.
Then it was withdrawn. After two weeks of public opposition, the Cabinet pulled the Bill on September 3. The government says it will put it in the public domain and bring it back in a changed form.
Sources: Outlook, Aug 31, 2026; The Week and Deccan Herald, Sept 3, 2026.
Each square is 2 acres. Lalbagh is about 240 acres (Deccan Herald; Karnataka Tourism). Red is the 5% the withdrawn Bill would have allowed.
The reports behind this don't hold up.
Every big project needs a Detailed Project Report, or DPR. It is the proof that the project makes sense. Here is what happened to these.
Two stories that cannot both be true
The approved big-tunnel report said it would be done by 2031.
To justify the new short tunnel, the same agency's report said the big one would take nearly a decade.
Sources: Deccan Herald (Nov 2024, Feb 2025, Oct 2025, editorial); Swarajya on the expert committee.
BMLTA vs B-SMILE, explained with football.
Two bodies with similar sounding names. They do opposite jobs.
Bengaluru Metropolitan Land Transport Authority. Created by law in 2022, after years of citizens asking for it.
Its job: make one plan for metro, buses and roads together. Check every big transport project against that plan before it starts.
Bengaluru Smart Infrastructure Ltd. A government-owned company. Not elected.
Its job: design, tender and build projects. It is behind the flyovers and the big tunnel.
A referee exists so that a player cannot decide the rules mid-game. Now watch what happened.
Step one. BMLTA reviewed the big tunnel. It found the project did not fit Bengaluru's metro-first mobility plan, which targets 70% of trips on public transport by 2035. It warned tunnel roads push people towards cars.
Step two. On August 24, 2026, the Assembly passed an amendment without debate. Projects started between 2022 and the new rules are now deemed to have been undertaken under the Act.
Step three. The same day, a second Bill let up to 5% of any government park be given away for public projects. That one was withdrawn on September 3 after protests. The BMLTA amendment still stands.
The government says the change keeps decisions consistent. Bengaluru South MP Tejasvi Surya says it hands a retrospective pass to projects worth close to ₹1 lakh crore. The amendment does not name the tunnel.
Source: Outlook, Aug 31, 2026, citing The Indian Express; Citizen Matters on the BMLTA rules.
What it costs, as tendered.
The estimates are the government's. So are the tender results. Here they are side by side.
Bengaluru Road Plan
Sources: The Hindu (Aug 14, 2026) via PressReader; Outlook (Aug 31, 2026); The News Minute (Sept 16, 2026). Tunnel figures: estimate ₹17,698 cr, lowest bid ₹22,267 cr. The tunnel contract has not been awarded yet. Consultation quote: Indiranagar residents to The Federal, June 2026.
What the government says.
You should hear it in their words, and then decide.
Sources: Outlook (Aug 31, 2026); The Federal (June 13, 2026); The News Minute (Sept 16, 2026).
What actually moves people.
Metro, suburban rail, bus lanes and footpaths share one property. Each carries more people as the city grows, because the capacity is added to a network instead of to a queue. That is the comparison every document on this page is really about.
Three questions Bengaluru should be able to answer
- Does every project get a BMLTA review before work starts?That is what the 2022 law was written for.
- Are the project reports, traffic studies, tree counts and lake studies public?Some are. The ones that decide the case are not.
- Are the people who live on the road consulted before the tender?So far, the objections have arrived after it.
These are not traffic solutions. They are transparency questions, and every one of them is answerable.
Don't take our word for it.
Read the documents. They are public, thanks to OpenCity. Then decide what you think Bengaluru should build.
This city has done this before.
Reading a project report and saying so out loud sounds like a small act. In Bengaluru it has a track record.
The parks law, 2026
Passed on August 24 without debate. Residents, resident welfare associations, environmental groups and both opposition parties objected for ten days straight. The Cabinet withdrew it on September 3 and said it would publish the Bill for public discussion first.
Source: The Week, Deccan Herald, Sept 3, 2026.
The steel flyover, 2017
A ₹1,791 crore steel flyover from Basaveshwara Circle to Hebbal, cleared by the Cabinet in 2016, with about 800 trees to be felled. Citizens formed a human chain along the route. The National Green Tribunal stayed it, and in 2017 the government cancelled it.
Sources: Deccan Herald (Cabinet approval and cancellation); Hindustan Times (NGT stay, 2017).
The first elevated corridor, 2019
An earlier elevated corridor network, already tendered. After protests under one demand, cancel the tender, the project was put on hold and the Chief Minister of the day agreed to a public consultation. The current corridors are the same idea, returning.
Source: Deccan Herald, 2019.
Ride apps, September 2026
Complaints about fare prompts that nudged riders to pay more before a ride was confirmed. On September 15, the Central Consumer Protection Authority fined Rapido ₹10 lakh for dark patterns and misleading practices. Uber and Ola are still under examination.
Source: Deccan Herald, Business Standard, Sept 15, 2026.
None of these were won by outrage. They were won by people reading the document, finding the specific thing that was wrong with it, and saying it in public, in numbers, until it could not be ignored.
Each one is small. A Bill pulled back is not a Bill repealed, and the parks amendment may return in another form. But a project that has to explain itself is already a different project.
On October 11, the city held hands again.
At 11 am, people stood hand in hand along Indiranagar's 80 Feet, 100 Feet and CMH roads. This is the route the Indiranagar corridor would take.
Most of them were young. Parishioners, nuns and the parish priest of Resurrection Church joined in; they say the church's Mother Mary grotto could be affected. Protesters say a banyan tree and a temple outside Chinmaya Mission Hospital also fall within the alignment.
Across town, more than 100 people held hands near Rose Garden Junction, against an 18.5 km tolled corridor from Ragigudda to Kanakapura Road. Their point: the metro's Green Line already connects both ends.
The organisers, the Dear DK campaign, say they are not against infrastructure. Their question is the one this page has been asking from stop 1. Will these projects actually solve the problem, and who checked?
flyovers Bengaluru has built in the last 20 years, by the organisers' count. They want other options explored before 13 more are built.
What they asked for
- Cancel the tenders for all 13 elevated corridors.Stop before the contracts are signed.
- Move the money, within 90 days.To mobility projects chosen on IISc's advice.
- Bring back the referee.Dissolve B-SMILE and let the BMLTA plan, as the 2022 law intended.
Two days earlier, the paperwork had already cracked.
On October 9 the government cancelled the tenders for nine of the eleven flyovers. Its own review panel had read the tender papers and found that they broke procurement rules. They mixed the national highway rulebook with the state's works code. They added conditions neither rulebook allows. And they counted rural roads and rail overbridges as experience for dense city flyovers.
The order cites those rules, not the protests. No contracts were signed. Deposits are being refunded.
But cancelled is not scrapped. All nine will be tendered again. Only the bidding starts over.
The referee's story moved too. An RTI reply made public on October 10 shows that 209 objections were filed against the rule that lets these projects skip the BMLTA's review from stop 8. Almost all of them asked for it to go. It was kept, unchanged.
And the week before the Indiranagar chain, residents in north Bengaluru formed human chains around the 1,128 trees marked for the Hebbal short tunnel.
Where it stands now
- Nine flyoversTenders cancelled on October 9. Fresh bids ordered.
- Two tolled corridorsIncluding 28 km past Ulsoor Lake. Tendered in August, not part of the cancellation.
- Hebbal to Silk Board tunnelLowest bid ₹22,267 crore. Awaiting a Cabinet decision.
- Hebbal short tunnelExcavation underway. A case on the lake is before the High Court.
- The BMLTA exemptionStill in force. The amended Act awaits the Governor's assent.
Bengaluru doesn't just need more infrastructure. It needs better public scrutiny of the infrastructure it builds.
The re-tender is the next chance to do that. Before the bids this time, not after.
Bengaluru residents have already written the letter.
Dear DK is a citizens' campaign asking the government to cancel the flyover tenders, move the money to mobility projects on IISc's advice, and let the BMLTA do the planning. Reading it takes two minutes. Signing it takes one.
Sources: Deccan Herald (Oct 10 and Oct 12, 2026); The News Minute (Oct 12, 2026); The South First (Oct 11, 2026); News Karnataka (Sept 8, 2026); Urban Acres (Oct 7, 2026); ThePrint (Oct 6, 2026); The South First (Aug 23, 2026); deardk.com.
Sources
- Deccan Herald: Residents demand scrapping of OMR-Indiranagar-Madiwala flyover (Oct 12, 2026)
- Deccan Herald: Hundreds join hands against proposed flyovers (Oct 12, 2026)
- The News Minute: Dear DK human chains (Oct 12, 2026)
- The South First: Rose Garden Junction human chain (Oct 11, 2026)
- Deccan Herald: Govt cancels tenders for 8 flyovers over violations (Oct 10, 2026)
- Urban Acres: ₹3,060 crore flyover tenders cancelled (Oct 7, 2026)
- Deccan Herald: BMLTA rule stands despite 209 objections (Oct 10, 2026)
- ThePrint: Hebbal short tunnel and its trees (Oct 6, 2026)
- News Karnataka: Dear DK, Flyover Yaake? (Sept 8, 2026)
- The South First: Tunnel bid not yet awarded (Aug 23, 2026)
- The News Minute: Inside the saga of the Ejipura flyover
- OpenCity: Hebbal to Silk Board tunnel DPRs
- OpenCity: Elevated road corridor documents
- OpenCity: Explainer, Bengaluru elevated corridors 2026
- OpenCity: BDA Revised Master Plan 2031
- The Hindu: B-SMILE awards 9 elevated corridors (Aug 14, 2026)
- Outlook: Why Karnataka changed park land and BMLTA rules (Aug 31, 2026)
- The News Minute: Hebbal tunnel and flood risk (Sept 16, 2026)
- Deccan Herald: Not 89, over 749 trees (June 22, 2026)
- The Federal: Indiranagar flyover uproar (June 13, 2026)
- Deccan Herald: Penalty on tunnel road consultant
- Deccan Herald editorial: 121 shortcomings in the DPR
- Deccan Herald: 4 years vs a decade
- Deccan Herald: DPR made in 3 months
- Deccan Herald: 28 km tolled flyover
- Deccan Herald: IISc study, flyover vs metro
- Down To Earth: Metro carries 40x a traffic lane
- Citizen Matters: BMLTA and its rules
- The Week: Karnataka withdraws the parks Bill (Sept 3, 2026)
- Deccan Herald: CCPA fines Rapido over dark patterns (Sept 15, 2026)
- Deccan Herald: Steel bridge scrapped, elevated corridor on hold
- Deccan Herald: The Dear DK campaign
- Deccan Herald: Cabinet approves the ₹1,791 crore steel flyover (2016)
- Deccan Herald: Government cancels the steel flyover (2017)
- Deccan Herald: Protests against the earlier elevated corridor (2019)
- Deccan Herald: Lalbagh, the 240 acre botanical garden
- Dear DK: Citizens' open letter and FAQ
- Business Today, on transport department data: 87 lakh two-wheelers of 1.28 crore vehicles